Mina Zayed Container Berths 3 and 4

Client: Public Works Department, Government of Abu Dhabi
Consultant: Sir Alexander Gibbs and Partners
Location: Abu Dhabi Port
Started: June, 1988
Completed: January, 1990
Value: Dhs 4,500,000

 

Electrical and Mechanical services for the container emptying shed extension, area 7,910 sq. m.; the transit shed No. 3, area 5,850 sq. m. and the container repair shed, area 840 sq.m.

Civil Value: Dhs 0.00
Peak Manpower: 0

 

Mechanical Details

Installation and testing and commissioning of DI fire mains, fire hydrants, valves and fire hose reels.

The installation, testing and commissioning of ABS water main pipes for the Mina Zayed container berths 3 and 4 areas.

Air conditioning and ventilation of the office areas of the sheds.

Mechanical Value: Dhs 1,500,000.00
Peak Manpower: 15

 

Electrical Details

Supply, installation, testing and commissioning of lighting, small power, telephone system and fire alarm system for the sheds.

Supply, installation, testing and commissioning of area lighting consisting of thirty masts thirty meters high.

Supply, installation, testing and commissioning of 11/33.3 KV substation consisting of 1500 KVA transformer. 3.3KV switchgear with the associated metering panel and other accessories.

Electrical Value: Dhs 3,000,000.00
Peak Manpower: 10

 