| Client: | Capital Investments |
| Consultant: | Khatib & Alami |
| Location: | Jumeirah Lakes, Dubai |
| Started: | May 2006 |
| Completion Date: | November 2008 |
| Value (Dhs.): | 196,931,901 |
The construction, completion, commissioning and maintenance of a commercial / residential development located in Jumeirah Lake Towers Project Area, Dubai, with four basement levels, ground floor, forty-four typical floors and roof, with associated external works. The building features a gymnasium, steam room,, sauna, jacuzzi and swimming pool and is topped with a decorative crown-like feature in steel construction.
Civil Details
| Total Plot Area: | 2,632 m2 |
| Total Built-Up Area: | 68,074 m2 |
| Concrete: | 38,266 m3 |
| Formwork: | 169,466 m2 |
| Rebar: | 7,995,000 kg |
| Blockwork: | 76,455 m2 |
| Plastering: | 110,698 m2 |
| Tiling Works: | 70,690 m2 |
| Elevator: | 4 |
| Civil Value (Dhs.): | 137,513,973 |
| Peak Manpower: | 408 |
Mechanical Details
The mechanical works for the project feature the following:
A complete HVAC system, complete with all required heat exchangers, FAHUs and FCUs, centrifugal exhaust fans and pressurising fans, AC controls. Complete fresh water supply and drainage system, A fire fighting system including sprinklers, hoses, cabinets The latest model of building management system.
| Mechanical Value (Dhs.): | 32,967,558 |
| Peak Manpower: | 80 |
Electrical Details
Installation, testing and commissioning of:
Small power and lighting including conduiting, wiring, wiring accessories and fixtures and Lighting control system. Power distribution including main distribution boards, submain, isolators, starters and control panels, Telephone/data system, Bus bar riser and Master Antenna TV system/PA system and Video Intercom system, CCTV system/Access control.
| Electrical Value (Dhs.): | 26,450,370 |
| Peak Manpower: | 48 |
| Total Manpower: | 536 |