| Client: | International Capital Trading |
| Main Contractor: | Pivot Engineering and General Contracting Company LLC |
| Consultant: | Ewan Architectural Engineering Consultancy |
| Location: | Mohammed Bin Zayed City, Abu Dhabi |
| Started: | April 2009 |
| Completion Date: | December 2010 |
| Value: | 260,000,000 |
The construction, completion and maintenance of 170 villas at Mohammed Bin Zayed City. All the villas have 2 floors (Ground and First floor). The project scope includes Club House, Swimming Pool, 2 Playgrounds, Multipurpose Hall, Mosque, Substations, Guardhouses, Public Parking Areas, Soil Investigation, Landscape and Boundary Walls and all associated external works.
Civil Details
| Total Plot Area: | 78,907 m2 |
| Total Built-Up Area: | 62,000 m2 |
| Concrete: | 30,564 m3 |
| Formwork: | 190,108 m2 |
| Rebar: | 4,940,059 kg |
| Blockwork: | 108,069 m2 |
| Plastering: | 264,279 m2 |
| Tiling Works: | 76,426 m2 |
| Civil Value (Dhs.): | 188,550,000 |
| Peak Manpower: | 1279 |
Mechanical Details
HVAC systems including ducted split units, decorative split units, packaged units and all required exhaust fans and accessories The supply and installation of all plumbing and drainage, including hot and cold water piping with all related accessories. All sanitary fixtures and accessories are supplied and installed. A complete storm water drainage system. A complete fire fighting infrastructure system including DI pipes, fire hydrants and fire cabinets
| Mechanical Value (Dhs.): | 46,643,480 |
| Peak Manpower: | 162 |
Electrical Details
Installation, testing and commissioning of:
Small power and lighting including conduiting, wiring, wiring accessories and lighting fixtures. Power distribution including main distribution boards, sub-main distribution boards, isolators, starters, control panels and cabling.
| Electrical Value (Dhs.): | 24,806,520 |
| Peak Manpower: | 141 |
| Total Manpower: | 1582 |