| Client: | Private Property Management |
| Consultant: | Arkan Architects and Consultants |
| Location: | Abu Dhabi |
| Started: | August 2006 |
| Completion Date: | April 2010 |
| Value(Dhs): | 272,750,000 |
The project is a prestigious new tower overlooking Abu Dhabi’s New Corniche road next to the landmark Bainunah Tower. It is a commercial building comprising of three basement floors, part basement floor for air conditioning equipment, ground floor, four office floors and twenty-two residential floors including health club and a service floor. Also included is the electric substation building for the tower.
Civil Details
| Total Plot Area: | 1,891 m2 |
| Total Built-Up Area: | 76,071 m2 |
| Concrete: | 22,580 m3 |
| Hollow Core Slab: | 4,934 m2 |
| Formwork: | 112,355 m2 |
| Rebar: | 4,907,522 kg |
| Blockwork: | 60,075 m2 |
| Plastering: | 113,385 m2 |
| Tiling Works: | 84,894m2 |
| Elevator: | 6 |
| Civil Value (Dhs.): | 210,750,000 |
| Peak Manpower: | 509 |
Mechanical Details
The mechanical works for the project feature the following:
A complete HVAC system, comprising 3 water cooled centrifugal chillers and three cooling towers, complete with all AHUs and FCUs. Complete fresh water supply and drainage system. A fire fighting system including all hoses, cabinets and accessories. Complete LPG system. The latest model of building management system.
| Mechanical Value (Dhs.): | 38,815,935 |
| Peak Manpower: | 65 |
Electrical Details
The electrical works for the project feature the following:
Relocation of the existing substation with all associated works. Five transformers of 1500kVA capacity. Lighting, CCTV, MATV and small power systems. All required cabling including conduits, cable trays and all accessories. Complete fire alarm system. A diesel generator of 750 kW capacity. All required LV panels.
| Electrical Value (Dhs.): | 23,184,065 |
| Peak Manpower: | 40 |
| Total Manpower: | 536 |