| Client: | Al Barshaa Real Estate Co. |
| Main Contractor: | Pivot |
| Project Manager: | PROJACS |
| Consultant: | ZAS Architecture |
| Location: | Barsha First, Dubai, UAE |
| Started: | April 2008 |
| Completion Date: | May 2009 |
| Value (Dhs.): | 94,077,956 |
The construction, completion, commissioning, maintenance of a glass and GRC clad reinforced concrete structure of three basements, six typical floors and a roof floor, that will house the executive offices for Barshaa Real Estate.
Civil Details
| Total Plot Area: | 3,158 m2 |
| Total Built-Up Area: | 28,170 m2 |
| Concrete: | 13,599 m3 |
| Formwork: | 38,827 m2 |
| Rebar: | 1,935,781 kg |
| Blockwork: | 6,721 m2 |
| Plastering: | 4,127 m2 |
| Tiling Works: | 9,536 m2 |
| Elevators: | 4 |
| Civil Value (Dhs.): | 68,167,956 |
| Peak Manpower: | 231 |
Mechanical Details
The mechanical works for the project feature the following:
All sanitary fittings. Cold water supply system including storage tanks and distribution system to all fixtures and equipment. Hot water supply to al fixtures. Air-conditioning works.
| Mechanical Value (Dhs.): | 13,420,564 |
| Peak Manpower: | 28 |
Electrical Details
The electrical works for the project feature the following:
LV panel and switchgear. Submain distribution cabling Power accessories and switchgear. Lighting points, wiring, switches. Analogue addressable fire alarm system. MATV/satellite antenna and distribution cabling. CATV system. Telephone system including wiring, and accessories. Lightning protection system and earthing network.
| Electrical Value (Dhs.): | 12,489,436 |
| Peak Manpower: | 20 |
| Total Manpower: | 279 |