| Client: | Abu Dhabi Municipality |
| Consultant: | Arab Office for Planning and Architecture |
| Location: | Al Heeliyah, Abu Dhabi |
| Started: | September, 2002 |
| Completed: | March, 2004 |
| Value: | Dhs 57,230,000 |
The construction of low-cost housing units in the outlying area of Abu Dhabi city.
Each villa is comprised of two storeys and has a total floor area of 485 m2. The construction is cast-in-situ concrete. Depending upon the existing ground conditions, each unit is built on piles or a raft foundation.
The villas are situated on plots of 46 by 46 metres, enclosed by an external boundary wall constructed from pre-cast concrete panels.
| Civil Value: | Dhs 49,580,000.00 |
| Peak Manpower: | 200 |
Mechanical Details
The supply and installation of all plumbing and drainage, including hot and cold water piping with all related accessories, ground level and roof water tanks and pumps.
All sanitary fixtures and accessories are supplied and installed.
Split unit AC is provided.
| Mechanical Value: | Dhs 4,000,000.00 |
| Peak Manpower: | 35 |
Electrical Details
Small power and lighting including conduiting, wiring, wiring accessories and lighting fixtures.
| Electrical Value: | Dhs 3,650,000.00 |
| Peak Manpower: | 25 |